WSC notifies contractors it will claim for cost of delays
- Weather delays Gas Deliveries
- Details on sewage treatment plant contracts released
- Sewage treatment plant near Mgarr ix-Xini now completed
- WSC replies to criticism in statement by AD
- MEPA and Polidano cooperate…again! – FAA
- AD calls for sewage plant at Wied il-Mielah
- Astra Folk Group off to Miranda de Ebro, North of Spain
- ETC removes 1,858 people from unemployment register
- Imperial Gozo Yacht Club – G2-Sagra Famiglia Cup
- Workers assaulted and threatened at San Blas
- Passenger movements down 4.2% in September
- The Coldest February in Gozo for 83 Years
- Full-time employment figures down for last year
- Enemalta announce sharp rise in LPG prices
- Farsons reports to shareholders on difficult year
In line with the directive set out by the Minister for Investment, Industry and Information Technology to the Board of Directors of the Water Services Corporation in his letter of the 9th August 2007, the Corporation has now informed its contractors working on the development of the sewage treatment plants that it intends to make claims to recover the costs of their delay in delivering the work on time.
The Gozo plant, which was scheduled to be commissioned by mid-September 2007, is being developed for the Corporation by Degremont S.p.A. The Malta (North) plant, scheduled for commissioning by the end of September 2007, is being developed for the Corporation by IBI S.p.A. and the Polidano Group.